Five US Grid Operators Face FERC Deadline on Data-Centre Power Rules
WASHINGTON — Five of America’s regional grid operators face a Monday deadline to answer federal regulators over how giant electricity customers, above all data centres, connect to the power grid and who pays for the upgrades they need.
PJM Interconnection, the New York ISO, the Midcontinent ISO, California ISO and ISO New England must file responses to Federal Energy Regulatory Commission show-cause orders by 5 p.m. Eastern on Monday, 16 November. A sixth operator, Southwest Power Pool, has until Friday, 20 November.
The filings are the next step in a process FERC opened on 18 June, when it issued six separate orders under section 206 of the Federal Power Act — one for each regional operator, running from docket EL26-67 for PJM through EL26-72 for ISO New England. The commission made a preliminary finding that existing tariffs may be unjust, unreasonable or unduly discriminatory because they do not adequately govern large-load connections.
What FERC asked for
At issue is the surge in requests from data centres and other industrial customers to draw tens or hundreds of megawatts from the grid, driven in part by demand for AI chips and the computing power behind them. FERC suggested a large load of 50 megawatts or more at a single site, connected above roughly 69 kilovolts and not already in a co-location arrangement, was a reasonable starting definition.
The commission asked operators to address five areas: how large-load applications are handled, transparency over upgrade costs, financial protection for other customers, co-location — where a customer sits beside a power plant — and flexible transmission service for loads willing to be curtailed. It also wants coordinated study of nearby generation and load, so a new data centre and the power plant meant to serve it are assessed together.
The original 60-day response period would have expired in August. The commission granted abeyances while operators developed their answers, pushing the deadline to November.
California and New England move first
California’s operator has already settled its answer. CAISO’s Board of Governors approved a 50-megawatt large-load framework on 28 October, and the operator plans to file the package with FERC by the 16 November deadline. Data Center Dynamics reported that the proposal creates a flexible interim service letting large customers connect before the grid upgrades they need are finished, and allows the operator to disconnect them remotely when reliability requires it.
“Our response to the FERC order to show cause will improve planning and operational awareness of new large loads on the system, prevent cost-shifting, encourage flexibility and expedite large load energization,” CAISO president and chief executive Elliot Mainzer said.
ISO New England filed its own proposal this week, for a large-load application and study process to take effect on 1 June 2027. It defines a large load as a commercial or industrial customer at a single site with a gross peak demand of 50 megawatts or more, connecting at more than 60 kilovolts. The operator said the process is designed to preserve reliability and avoid shifting costs to consumers.
PJM has already had a 50-megawatt single-site definition accepted by FERC, in an October order, and MISO has proposed pairing loads of 200 megawatts or more with nearby generation under its Large Asset Reliability Study framework.
Who pays for the upgrades
The cost question is the sharpest part of the debate. Grid operators and consumer advocates warn that if a data centre triggers a costly transmission upgrade and then shrinks, cancels or never arrives, households and small businesses can end up carrying the bill.
Regulators elsewhere have already moved. In October, FERC approved Duke Energy Carolinas’ large-load terms, under which new large loads pay a committed revenue contribution equal to 75 per cent of their scheduled megawatts for 15 years after the upgrades they need enter service. An Edison Electric Institute summary from October counts 25 states with at least one approved large-load tariff and eight more with tariffs pending.
The California Energy Commission has forecast 1.8 gigawatts of data-centre load growth in the state by 2030 — a figure that covers data centres only, not every customer that would fall under the 50-megawatt threshold.
What happens next
Monday’s filings are party responses, not final commission findings. They do not approve any named data centre, customer contract, transmission project or generation resource, and they do not settle retail rates, land use or permits, which remain state and local matters.
Once the operators file, other parties will have 30 days to answer or protest, putting most comment windows around 16 December. FERC will then decide whether each operator’s tariffs must change — and, if so, on what terms. Until it acts, today’s tariffs still govern, and the queue of data centres waiting for power keeps growing.